Question: 1 If a proejct has a net present value equal to zero, then: The present value of the cash inflows exceeds the initial cost of

1
If a proejct has a net present value equal to zero, then:
The present value of the cash inflows exceeds the initial cost of the project.
The project produces a rate of return that equals the required rate of return.
The project will not increase the value of the company.
Any delay in recelving the projected cash inflows will casue the project to have a negative net present value.
1.2, and 3 only
2, and 4 only
2, and 3 only.
and 4 only.
2,3, and 4 only.
1 If a proejct has a net present value equal to