Question: 1. If the standard for direct materials is 5 ft. at $10 per square foot for each unit produced what is the direct materials price
1.
If the standard for direct materials is 5 ft. at $10 per square foot for each unit produced what is the direct materials price variance if 100 units are produced, 510 ft. are used and $9 per square foot is paid?
Select one:
a. 510 favorable
b. $510 unfavorable
c. $100 unfavorable
d. $100 favorable