Question: 1. In an M/M/ 1 queueing system, the arrival rate is 6 customers per hour and the service rate is 9 customers per hour. If
1. In an M/M/1 queueing system, the arrival rate is 6 customers per hour and the service rate is 9 customers per hour. If the service process is automated (resulting in no variation in service times but the same service rate), what will be the resulting performance measurements? ( ROUND YOUR ANSWER TO 3 DECIMAL PLACES)
a. What is the utilization? (Round your answer to 3 decimal places)
b. What is the expected number of customers in the system (L)? (Round your answer to 3 decimal places)
c. What is the expected waiting time (in hours) for the system (W)? (Round your answer to 3 decimal places)
d. What is the expected number of customers in the queue(Lq)? (Round your answer to 3 decimal places)
e. What is the expected waiting time (in hours) in the queue (Wq)? (Round your answer to 3 decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts