Question: 1) In this phase, the product is made using the intended production system. Phase 1: Concept development Phase 2: System-level design Phase 3: Detail design
1) In this phase, the product is made using the intended production system.
Phase 1: Concept development
Phase 2: System-level design
Phase 3: Detail design
Phase 4: Testing and refinement
Phase 5: Production ramp-up
2)
The inherent value of the product in the marketplace is:
a.conformance quality.
b.overall quality.
c.customer quality.
d.meaningful quality.
e.design quality.
3)
A project in which individual team members report to two different bosses, a project manager and their own functional manager, is based on which of the following organization structures?
a.Matrix project
b.Integrated task force
c.Functional project
d.Pure project
e.Cross-functional flexible team
4)
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:
| Activity | Immediate Predecessor | Time in Days |
| A | None | 2 |
| B | A | 1 |
| C | A | 2 |
| D | B and C | 3 |
| E | D | 1 |
Using the CPM, which activities have slack in this project?