Question: 1 . MATERIALS MANAGEMENT ( 3 * 7 = 2 1 marks, 3 marks for each component ) A manufacturing organization needs to plan the
MATERIALS MANAGEMENT marks, marks for each component
A manufacturing organization needs to plan the materials required for the next six weeks for the manufacture of its endproduct Product A as per a master production schedule. In addition to the end product, there is an independent requirement of Component C as it is sold as a spare in the market. The master production schedule for both the end product and the spares are given in Table In order to assemble one unit of Product A Components B to G are required. Figure shows the product structure. In the figure, the number alongside each component denotes the number of each component required to assemble its immediate parent. An extract of the inventory status Table reveals the inventory on hand. There are no pending orders for delivery. Different lotsizing rules are used for the components of Product A Moreover, the components have different lead times. All this information is available in Table Perform an MRP exercise to estimate the quantity and timing of the components required for the manufacture of Product A as per the MPS
Figure : The Product Structure
Table Master Production Schedule for the Next Six Periods
Period Period Period Period Period Period
Product A
Component C
Table Inventory Status, Lead Time, and LotSizing Rule
Component OnHand Lead Time Lot Size
A Lot for Lot
B Lot for Lot
C Lot for Lot
D periods
E periods
F
G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock