Question: 1. On a variance analysis, a manager should focus on explaining: Select one: a. Items that are related to labor and materials only b. Items
1. On a variance analysis, a manager should focus on explaining:
Select one:
a. Items that are related to labor and materials only
b. Items that are over budget by any amount
c. Items that vary from budget by a significant amount
d. Every item on the operating report