Question: 1 . On June 1 2 , 2 0 0 2 , Alpha Corporation was awarded a $ 1 6 0 , 0 0 0
On June Alpha Corporation was awarded a $ contract for testing a product. The contract consisted of $ for labor and materials, and the remaining $ was profit. The contract had a scheduled start date of July The network logic, as defined by the project manager by the customer resulted in the following project planning budget:
Activity
AB
AC
AD
BC
BE
CF
DF
EF
FG
On August the executive steering committee received the following report indicating the status of the project at the end of the eighth week:
Activity Complete
Based on Weeks Actual Cost Time Remaining Weeks
AB $
AC $
AD $
BC $
BE $
The steering committee could not identify the real status of the project from the brief report. Even after comparing this brief status report with the project planning budget above, the real status was not clear.
Management instructed the project manager to prepare a better status report that depicted the true status of the project at the end of week eight. Your assignment is to prepare a table using the template available in the Blackboard assignment folder labelled Alpha Project Status Report. Submit the completed Excel spreadsheet along with the rest of your assignment. pts
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock