Question: 1 . On June 1 2 , 2 0 0 2 , Alpha Corporation was awarded a $ 1 6 0 , 0 0 0

1. On June 12,2002, Alpha Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, and the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager by the customer resulted in the following project planning budget:
Activity 123456789101112131415
AB 2000200030003000400040003000
AC 3000300030004000400040004000200020001000
AD 50005000600040004000400030001000
BC 3000400040005000
BE 60006000
CF 200030003000
DF 30003000300040004000
EF 20002000
FG 3000
On August 27,2002, the executive steering committee received the following report indicating the status of the project at the end of the eighth week:
Activity % Complete
(Based on Weeks) Actual Cost Time Remaining (Weeks)
AB 100 $23,5000
AC 70 $19,2003
AD 75 $37,5002
BC 75 $8,0001
BE 50 $5,5001
The steering committee could not identify the real status of the project from the brief report. Even after comparing this brief status report with the project planning budget above, the real status was not clear.
Management instructed the project manager to prepare a better status report that depicted the true status of the project at the end of week eight. Your assignment is to prepare a table using the template available in the Blackboard assignment folder labelled Alpha Project Status Report. Submit the completed Excel spreadsheet along with the rest of your assignment. (16pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!