Question: 1 . On the map shown in Figure 1 , a site will be developed as an office building ( Land Use: 7 0 1

1. On the map shown in Figure 1, a site will be developed as an office building (Land Use: 701,
Weekday Urban Peak Period Parking Demand) with a gross leasable area (x) of 418.25 thousand
square feet. Conduct a traffic impact study and a parking study for this site. The time points to be
considered are:
1. The present time
2. The time when the development becomes fully operational (3 years from the present time;
3% annual growth of background traffic)
3. A target year set at 7 years from the time when the development becomes operation (1.5%
annual growth of background traffic)
The trip-generation equations are:
A.M. peak-hour trips (T): ln (T)=0.8 ln (x)+2 with 90% enter and 10% exit
P.M. peak-hour trips (T): ln (T)0.9 ln (x)+1 with 15% enter and 85% exit
It is likely that signalized control should be placed at the site access point. This T intersection
along with intersections I1 and I2 must be analyzed for one-hour in the A.M. and P.M. weekday peak
period. New signal timings should be estimated and up to one additional lane per approach may be placed
if the approach LOS is worse than a C. Estimates of through traffic at the access point should result from
the volumes of intersection I2. All three intersections must operate under compatible cycle lengths so that
arterial progression is maintained.
The expected modal splits are as follows:
Opening time (t +3): 80% drive alone, 20% car pool (occupancy 2.4)
Target time (t +10): 60% drive alone, 30% car pool (occupancy 2.0)
10% use rail transit
In t +3 and t +10 distribute volumes per lane so that flow rations are approximately equal.
These model splits should be used in both the traffic impact and the parking study. Figure 1 includes the
expected distribution of traffic. Existing conditions of intersections I1 and I2 are shown in Figure 2.
Figure 2
I1
I2
Include HCS outputs of the worst-case scenario (A.M. or P.M. peak period) for the operational and target
years.
Create the same tables as we did in the example problems in class.
2. Does the traffic coming in and out of the site, once built out, need a stop sign or signal lights
installed? Why or why not?
3. How many parking lots should there be for the office building?
4. How many handicap parking stalls should you include in the parking for this office building?
5. You, as a Transportation Engineer Planner, want to evaluate how to reduce crash and accidents in
the two intersections. First you see if congestion in the two intersections exist initially. If so, how
would you decrease the congestion and what initiatives can you use to reduce any crash and
accidents happening and why? Please cite any tables, figures, information, etc. that is used to back
up your case.
Problem one explanation:
Please Use Yellow time as 4 seconds and All Red as 2 seconds instead of what is shown on the
hand-out.
In addition, make sure you consider the occupancy per vehicle.
Use the percentages on Intersections one and two to divert the site traffic during operational and
target
years. In addition, use the same percentages for percent turns and throughs during the present time.
Example: If you calculated 100 vehicles exiting the site, then 50% is going right and the other 50% is
going left. Then take each of the volumes and distribute the volume in both intersections. So if 50%
of
the 100 vehicles are turning left then:
50 vehicles x 30% is turning right (100 x 15% is turning right)
50 vehicles x 10% is turning left (100 x 10% is turning left)
50 vehicles x 60% is going through (100 x 30% is turning right)
Do the same for the vehicles going into the site as well.
Then use interpolation to figure out the amount distributed in going through.
For the present time, use the percentages, as shown, to calculate the turns. For example, intersection
one has a south bound through-right and through-left shared. Therefore:
SB left =150 x 50%=75
SB right =200 x 30%=60
SB Through one =15075=75
SB Through two =20060=140
Total SB Through =140+75=215
Problem three explanation:
Compare the calculated parking generation to the number of vehicles during peak, going into the
office parking.On the map shown in Figure 1, a site will be developed as an office building (Land Use: 701, Weekday Urban Peak Period Parking Demand) with a gross leasable area (x) of 418.25 thousand square feet. Conduct a traffic impact study and a parking study for this site. The time points to be considered are:
The present time
The time when the development becomes fully operational (3 years from the present time
1 . On the map shown in Figure 1 , a site will be

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!