1. Perform a PERT analysis of the following project and find the probability of finishing the project...
Fantastic news! We've Found the answer you've been seeking!
Question:
1. Perform a PERT analysis of the following project and find the probability of finishing the project between 16 and 20 days inclusive.
2. Suppose it is known that the duration of a project is uniformly distributed between 24 months and 46 months. Find the probability that the project can be completed in 40 months or less.