Question: 1. Problem 11.01 (NPV) eBook Problem Walk-Through Project L requires an initial outlay at t= 0 of $60,000, its expected cash inflows are $11,000 per


1. Problem 11.01 (NPV) eBook Problem Walk-Through Project L requires an initial outlay at t= 0 of $60,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ 2. Problem 11.02 (IRR) E eBook Problem Walk-Through Project L requires an initial outlay at t= 0 of $80,421, its expected cash inflows are $13,000 per year for 10 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places. % Grade it Now Save & Continue 3. Problem 11.03 (MIRR)) 10 eBook Problem Walk-Through Project L requires an initial outlay at t= 0 of $75,000, its expected cash inflows are $8,000 per year for 9 years, and its WACC is 12%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. % 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts