Question: 1 Project completion time is: * 23 weeks 26.5 weeks 32 weeks 20 weeks None of the answers 2 Expected times of activities C &
1 Project completion time is: *
23 weeks
26.5 weeks
32 weeks
20 weeks
None of the answers
2 Expected times of activities C & F are respectively: *
1 &4
2 &9
6.5 &3
6 &2.5
None of the answers
3 Project variance is the _____________, and it is equal to *
sum of the variances of critical path activities; 5.416
sum of the variances of critical path activities; 4.146
sum of the variances of all activities; 3.541
sum of the variances of all activities; 3.543
None of the answers
4 Project Standard deviation is equal to *
2.327
1.436
2.877
1.957
None of the answers
5 Determine the "Project's Expected Date of Completion" if the probability of completion is 92.507% *
28.6 weeks
29.8 weeks
22.7 weeks
11 weeks
None of the answers
Preceding CA Activity A B D E F G H B AC E D F, G Optimistic 3 4 5 3 6 1 4 3 Most Likely 4 5 5 4 8 2 6 3 Pessimistic 8 6 11 5 13 6 8 12