Question: 1. (Project Management: deterministic network) The WBS and the precedence relationships are given as follows: Activity Time (days) Precedence Foundation 4 Framing 10 Foundation Plumbing

1. (Project Management: deterministic network)

1. (Project Management: deterministic network) The WBS and the precedence relationships are given as follows: Activity Time (days) Precedence Foundation 4 Framing 10 Foundation Plumbing 9 Framing Electrical 6 Framing Wall Board 8 Plumbing, Electrical Siding 16 Framing Paint Interior 5 Wall Board Paint Exterior 9 Siding Fixtures 6 Int. Paint, Ext. Paint a) Draw the AON (Activity-on-Node) network for this project. b) Calculate ES, EF, LF, LS, and Slack for each activity