Question: 1 . Question 1 - Read Exercise 1 in Chapter 6 from the textbook. Bases on the exercise, answer the following questions: Draw a Gantt
Question Read Exercise in Chapter from the textbook. Bases on the exercise, answer the following questions:
Draw a Gantt chart using MS Project.
Assuming a day week, find the critical path and project duration in days.
Given that each resource is aligned to each task, identify the resource constraints.
Using the MS project default, level the resources and determine the new project duration and Critical path.
Identify what alternative solutions minimum can be used to shorten the project duration without over allocating the resources.
Question Read Exercise of Chapter from the textbook. Based on the exercise, answer the following questions:
Determine cost and schedule variance.
Find the value of the cost performance index CPI and schedule performance index SPI
Find the Critical ratio of the project using Earned Value calculations.
Calculate Estimated remaining cost to completion ETC and Projected total cost estimated at completion EAC
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
