Question: 1. Scheduling table ( Charity Run ) Activity Description Duration (Weeks) Activity Predecessor A Planning a charity run 13 - B Choosing a route 3
1. Scheduling table ( Charity Run )
| Activity | Description | Duration (Weeks) | Activity Predecessor |
| A | Planning a charity run
| 13 | - |
| B | Choosing a route
| 3 | A |
| C | Legalities of a charity run
| 4 | B |
| D | Project Outputs
| 1 | C |
| E | Resources and Staff
| 3 | C,D |
| F | Cost budgeting | 1 | E |
| G | Establish guest numbers
| 9 | F |
| H | Accommodations
| 1 | G,F |
| I | Promote activities
| 8 | H |
| J | Define route logistics
| 7 | A,I |
| K | Collect Funds
| 17 | J |
| L | Undertake walk
| 1 | K |
| M | Completing the charity project
| 1 | L |
Questions
a) Draw a network diagram .
b) State the completion time .