Question: 1. show the work (formula included), spreadsheet/excel expected The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
1.

show the work (formula included), spreadsheet/excel expected
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Activity ABCDE C D E Time Estimates (weeks) m 35265 a 2 16 5 58893 8 9 b 7 529 answer format: 4 decimals (.) example: 0.9999 12 19 Activity Predecessor A A B,C D a. Using Table above, the expected time to complete the project is 32 answer format: 1 decimals (.) example: 0.9 weeks. b. Using Table above, the probability that the project could be completed in 35 weeks or less is approximately 0.8573Step by Step Solution