Question: 1 . Start: Obtain Building Permit ( 1 day ) 2 . Clear Lot and Grade for Slab ( 2 days ) 3 . Place

1. Start: Obtain Building Permit (1 day)
2. Clear Lot and Grade for Slab (2 days)
3. Place Concrete Forms, Reinforcement Rods, Sewer Lines (2 days)
4. Pour Slab (1 day)
5. Erect Wooden Frame, Including Roof (5 days)
6. Fasten Exterior Sheathing (2 days)
7. Install Rough Plumbing (3 days)
8. Install Rough Wiring (2 days)
9. Insulate Outside Walls (1 day, dependent on tasks 6,7,8, and 27)
10. Sheetrock and Plaster Inside Walls (3 days, dependent on task 9)
11. Do Rough Carpentry, Including Window and Door Frames (5 days)
12. Do Finish Carpentry: Cabinets, Trim Moldings, Paneling (10 days, dependent on tasks 10 and 11)
13. Sand, Stain, and Varnish Wood Paneling and Cabinets (3 days, dependent on task 12)
14. Lay Formica Counter Surfaces in Kitchen (1 day, dependent on task 13)
15. Install Tubs and Shower Basins (1 day, dependent on tasks 10 and 11)
16. Lay Flooring (Wood and Vinyl)(2 days, dependent on task 15)
17. Install Remaining Plumbing Fixtures (1 day, dependent on tasks 14 and 16)
18. Sand and Paint Interior Walls and Trim (5 days, dependent on task 17)
19. Lay Flooring (Wood and Vinyl)(2 days, dependent on task 18)
20. Install Remaining Plumbing Fixtures (2 days, dependent on task 18)
21. Install Kitchen Appliances (1 day, dependent on task 18)
22. Install Hot Water Heater (1 day, dependent on task 7)
23. Install Heating and Cooling Ducts (3 days, dependent on task 5)
24. Install Furnace and Air Conditioner (1 day, dependent on tasks 8 and 23)
25. Complete Exterior Trim (3 days, dependent on task 6)
26. Lay Brickwork (Exterior Walls plus Inside Fireplace)(5 days, dependent on task 25)
27. Shingle Roof (2 days, dependent on task 5)
28. Attach Gutters and Downspouts (2 days, dependent on tasks 26 and 27)
29. Paint Exterior Trim (2 days, dependent on task 28)
30. Place Insulation in Attic (1 day, dependent on tasks 10 and 26)
31. Grade, Lay Forms for Walks and Driveways (1 day, dependent on task 26)
32. Pour Walks and Driveway (1 day, dependent on task 31)
33. Finish Grading (1 day, dependent on tasks 32 and 37)
34. Landscape Yard (2 days, dependent on task 33)
35. Install Electrical Outlets, Switches, Lighting Fixtures (1 day, dependent on tasks 20,21,22, and 24)
36. Final Hookup of Electrical System (1 day, dependent on task 35)
37. Clean Up Interior and Exterior, Including Yard (1 day, dependent on tasks 19,29,30, and 35)
38. Lay Carpeting (2 days, dependent on task 37)
39. Attach Cabinet Fixtures (1 day, dependent on task 18)
40. Finish: Close Out House (1 day, dependent on tasks 34,36,38, and 39) create arrow diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!