Question: 1. Static versus flexible budget Static budgets present budgeted amounts based on fixed assumptions, whereas flexible budgets change base on activity level. A flexible budget
1. Static versus flexible budget
Static budgets present budgeted amounts based on fixed assumptions, whereas flexible budgets change base on activity level. A flexible budget is a static budget, restated at different leverls of activity.
Actual departmental expenses for the month of May for the Assembly department of Destin Enterprises are compared to a static budget in the Assembly Department Expenses report shown. A flexible budget, the Assembly Department Expenses Budget, is also presented for different levels of production.
Destin Enterprises Assembly Department Expenses for the Month of May
| Budget | ||
| Actual | (1,700 units) | |
| Variable cost: | ||
| Direct materials | $10,275 | $8,500 |
| Direct labor | 133,575 | 127,500 |
| Variable overhead | 61,650 | 59,500 |
| Total variable cost | $205,500 | $195,500 |
| Fixed cost | 1,000 | 1,000 |
| Total department costs | $206,500 | $196,500 |
Destin Enterprises Assembly Department Expenses Budget For the Month of May
| Units of production | 1,100 | 1,700 | 2,100 |
| Variable cost: | |||
| Direct materials | $5,500 | $8,500 | $10,500 |
| Direct labor | 82,500 | 127,500 | 157,500 |
| Variable overhead | 38,500 | 59,500 | 73,500 |
| Total variable cost | $126,500 | $195,500 | $241,500 |
| Fixed cost | 1,000 | 1,000 | 1,000 |
| Total department costs | $127,500 | $196,500 | $242,500 |
A. The Assembly Department Expenses report shows that the Assembly department spent $206,500, which is $10,000 over budget, in May. The Assembly department produced 1,870 units in May.
Is this good news or bad news? Please choice one from the following:
| Good news | |
| Bad news |
B. Seclect a statement to support your answer. Please choice one from the following:
| Destin produced fewer units at a higher than budgeted cost. | |
| Destin produced fewer units, but the cost to produce those units was less than budget. | |
| Destin produced more units but at a higher than budgeted cost. | |
| Destin produced more units for less cost. |