Question: 1. (TCOs A and B) A Monte Carlo analysis does all of the following, except (Points : 5) provide the probability of competing the project

1. (TCOs A and B) A Monte Carlo analysis does all of the following, except (Points : 5) provide the probability of competing the project on a given day.

determine what methodology to employ in risk management.

maintain the risk register.

evaluate the effectiveness of risk responses.

Question 2. 2. (TCO G) You are the project manager for a large financial industry project. You need to bring in some additional project team members for staff augmentation during your project. Which type of contract would likely be best in the situation? (Points : 5) Cost plus incentives

Time and materials

FPEPA

CPPC

Question 3. 3. (TCO D) You have been assigned as the project manager to develop a new software tool for a Fortune 100 software development company. During your risk management process you discovered that this new tool nicely complements the portfolio of software tools that this company has already developed. This would be considered a positive risk on your current risk register. What type of strategy would you employ to enhance this opportunity? (Points : 5) Transfer and Share

Exploit and Accept

Avoid and Mitigate

Exploit and Avoid

4. (TCO A and B) You are the project manager for a high dollar project for the public sector. Your boss asks you to describe a risk management process for (1) identifying project risks, (2) ranking project risks, and (3) developing appropriate responses for those risks. (Points : 20)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!