Question: 1. The backward pass in project network calculations determines the Latest time's activities can begin Earliest time's activities can be finished Critical path Both A

1. The backward pass in project network calculations determines the
Latest time's activities can begin
Earliest time's activities can be finished
Critical path
Both A and C are correct
A, B, and C are all correct


2. The second step in the defining of a project would be to
Analyze the strategic plan
Analyze the current budget plan
Establish project priorities
Select team members
Define the major objectives to meet the customer's needs


3. In practice, estimating processes are frequently classified as
Top down/bottom up
Rough/polished
Precise/order of magnitude
Draft/final
Both A and B are correct


4. The method used to collect information to use through all phases of the project life cycle is called
Responsibility matrix
Organization breakdown structure
Work breakdown structure
Priority matrix
Work package

5. Which of the following methods is not considered a top-down approach to estimating project time and cost?
Ratio
Template
Apportion
Function point
Learning curve


6. General and Administrative costs are usually allocated as a percent of the total of a direct cost such as labor, materials, or equipment.
True
False


7. Nodes on an AON project network represent:
An activity
An event
Responsibility
Both B and C are correct
Both A and B are correct

Step by Step Solution

3.49 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Lets go through each question and answer them step by step Question 1 The backward pass in project network calculations determines the 1 Latest times activities can begin 2 Earliest times activities c... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!