Question: 1 ) The dotted line represents different time cost values while performance is fixed. The project manager may select different performance scenarios while maintaining a

1) The dotted line represents different timecost values while performance is fixed. The project manager may select different performance scenarios while maintaining a constant level of performance. If the project moves from condition A to condition C, it has:
a) Increased in cost and decreased in duration.
b) Increased in cost and increased in duration.
c) Decreased in cost and increased in duration.
d) Decreased in cost and decreased in duration.