Question: 1 ) The dotted line represents different time cost values while performance is fixed. The project manager may select different performance scenarios while maintaining a
The dotted line represents different timecost values while performance is fixed. The project manager may select different performance scenarios while maintaining a constant level of performance. If the project moves from condition A to condition C it has:
a Increased in cost and decreased in duration.
b Increased in cost and increased in duration.
c Decreased in cost and increased in duration.
d Decreased in cost and decreased in duration.