Question: 1. The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes,

1. The following table lists the components
1. The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, and the direct components of cach item and, in brackets, the number of each component for each parent Given the following information, develop a material requirement plan for component that will yield 300 units of product Pat the start of week 6 Item Direct components Currently On-Hand Lead Time Order Quantity P A(1),B(1) 1 Lot-for-lot C(2) 120 1 100 B D(1) 0 2 400 90 1 350