Question: 1. The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
1. The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of 160 units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
b. Complete the last three rows of the record by using the L4L lot-sizing rule
LOT SIZE:FOQ = 160
lEAD TIME= 2 WEEKS
C. Complete the last three rows of the record by using the POQ lot-sizing rule, with P=2.
WEEK
|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross Requirments |
| 70 | 20 | 45 | 40 | 80 | 80 | 80 | 80 |
Scheduled Receipts |
| 160 |
|
|
|
|
|
|
|
Projected on hand inventory | 15 | ? | ? | ? | ? | ? | ? | ? | ? |
Planned Receipts |
| ? | ? | ? | ? | ? | ? | ? | ? |
Planned Order Releases |
| ? | ? | ? | ? | ? | ? | ? | ? |