Question: 1. The precedence chart is given below: Ammediate Optimistic Most Lilocly Pessimistion Activity Activity Activity Standard Variance 1. Perform critical path analyals. The critical path
1. The precedence chart is given below: Ammediate Optimistic Most Lilocly Pessimistion Activity Activity Activity Standard Variance 1. Perform critical path analyals. The critical path is and the project duration is around day. Use forward and backward passes approach ile jeractitioner approach. 2. Compute total slack and free slack for each activity. 3. Compute project variance (i.e) variance along critical path. Use Beta Distrbution for computing values. 4. Find the probsbility of completing this project within 32 days. Use Nomal Toble for computing the probability