1. The project management plan is the output of the planning process of project _____.
a. | integration management | c. | scope management |
b. | quality management | d. | procurement management |
Which of the following is an output of schedule control?
a. | Lessons-learned reports | c. | Resource requirements |
b. | Activity attributes | d. | Milestones list |
____ The cost performance index (CPI):
a. | indicates that a project is under budget if CPI is less than one. | c. | indicates that the planned and actual costs are equal if CPI is more than one. |
b. | can be used to estimate the projected cost of completing the project. | d. | is the ratio of earned value to planned value. |