Question: 1. The right to terminate a construction contract for default generally arises only when a non-material provision of the contract has been breached or a
1. The right to terminate a construction contract for default generally arises only when a non-material provision of the contract has been breached or a party has failed to perform a non-material obligation.
True
False
2. Time for performance is a material element of contracts performance when the contract states time is of the essence and there are set performance dates.
True
False
3. Repudiation is when a party (ie: a contractor) indicates by words or actions that they will not perform their contractual obligations
True
False