Question: 1. The right to terminate a construction contract for default generally arises only when a non-material provision of the contract has been breached or a

1. The right to terminate a construction contract for default generally arises only when a non-material provision of the contract has been breached or a party has failed to perform a non-material obligation.

True

False

2. Time for performance is a material element of contracts performance when the contract states time is of the essence and there are set performance dates.

True

False

3. Repudiation is when a party (ie: a contractor) indicates by words or actions that they will not perform their contractual obligations

True

False