Question: (1) The table shows activities data for a project. Activities A (Start) B D E F G I J (Finish) Duration (Days) Predecessors 0 10

(1) The table shows activities data for a

(1) The table shows activities data for a project. Activities A (Start) B D E F G I J (Finish) Duration (Days) Predecessors 0 10 A 12 A 13 A 35 B 25 8 D 12 E, F 4 F G 0 HI Task 1: Draw an Activity-on-Node network diagram for the project. (14 marks) Task 2: Calculate the minimum time required for the project and identify the Critical Path and critical activities for the project. (6 marks)