Question: 1. The transition from one phase to another within a project's life cycle (e.g. design to manufacturing) is typically marked by: A. Technical transfer or

1. The transition from one phase to another within a project's life cycle (e.g. design to manufacturing) is typically marked by:

A. Technical transfer or handoff

B. Deliverables

C. Milestones

D. Reviews

2. Ongoing operations and a project both have Initiating Processes, but only a project has __________.

A. Planning Processes

B. Closing Processes.

C. Control processing

D. Executing Processes

3. Project scope, time, and cost are often referred to as the:

A. Three-legged stool

B. Triple constraint

C. Project drivers

D. Standard constraints

4. Which one of the following is not an attribute of a project?

A. Definite starting date

B. Has no definite end date

C. Creates a product, service, or result

D. Requires resources

5. You are the project manager for a large software development project. You have concerns that one of the components of the Iron Triangle is slipping. Your project sponsor, Jim Bob, is not familiar with the Iron Triangle, so you explain the concept to him. What will be affected if any angle of the Iron Triangle is not kept in balance?

A. Cost

B. Quality

C. Time

D. Scope

6. Which of the following is not a Project Management Knowledge Area?

A. Project Integration Management

B. Project Change Management

C. Project Risk Management

D. Project Time Mana

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!