Question: 1 . There are three ( 3 ) machines on a production line. Defective rates of the machines are 6 % , 5 % ,

1. There are three (3) machines on a production line. Defective rates of the machines are 6%,5%, and 4% respectively. The employees are afforded 45 minutes per shift. The plant efficiency is 90%. The plant needs 30000 good quality products from an 8hr shift.
1.1 Determine the takt time.
1.2 Given that the scrap costs for pr 1,2, and 3 are R50, R40 and R80 respectively, calculate the total scrap costs.