Question: 1 To develop a company's competitive strategy, one must consider all of the following except? 2 Project stakeholders can be divided into internal and external
1 To develop a company's competitive strategy, one must consider all of the following except?
2 Project stakeholders can be divided into internal and external stakeholders internal. External stakeholders include:
a) Project sponsers
b) Project team
c) Government officials
d) Project support staff
3 A project manager is assigned to a project:
a) After signing the project charter
b) After the project initiation
c) At any time depending on the organization executive preferences
d)Before the project starts
4 When a supplier promises to deliver computer hardware so the project team can install a certain software on it this is called an:
a) External dependencies
b) Mandatory dependencies
c) Internal dependencies
d) Discretionary dependencies
5 A project for building a 3000 square feet house, the architect estimates that it will costs $150/sq. foot to a total of $4,50,000. This method of estimating a project cost is called:
a) Bottom-up estimate
b) Top-down estimate
c) Parametric estimate
d) Analogous estimate
6 Two tasks A and B. Task A duration is 6 days Task B duration is 4 days. If task B is dependent on Task A with a start to start dependency, task B must start:
a) 3 days before task A starts.
b) 2 days after task A finishes
c) At the same time as Task A
d) 2 days after Task A starts.
7 Two tasks A and B. Task A duration is 6 days Task B duration is 4 days. If task B is dependent on Task A with a Finish-to-finish dependency:
a) At the same time as task B
b) 2 days after task B finishes
c) 3 days before Task B starts
d) 2 days before task B starts