Question: 1. true or false: ABC allocates overhead costs to products based on input measres rather than output measures. 2. true or false: the more activities
1. true or false: ABC allocates overhead costs to products based on input measres rather than output measures.
2. true or false: the more activities tracked by activity based costing the mpe accurately overhead costs are assigned
3. true or false: facility level activities are carried out regardless of how many units are made, how many batches are run, or how many different products are made true falswe