Question: 1. UNEQUAL LIVES The NPV (required return is 10%) using the replacement chain approach for Project B for 4 years is a. $66,718 $75,000 c.
1. UNEQUAL LIVES
The NPV (required return is 10%) using the replacement chain approach for Project B for 4 years is
a. $66,718 $75,000 c. $61,787 d. None
T CASH FLOW PROJECT A CASH FLOW PROJECT B
0 (200,000) (80,000)
1 90,000 60,000
2 90,000 75,000
3 90,000
4 90,000
NPV $85,288
2. PREFERRED STOCK
The required return on a preferred stock with a $100 par value that has an annual dividend of 12% is currently 11%. What is the current market price?
(Rps = Div / Price)
a. $100 b. $109 c. $92 d. $88.35
3. BOND PROBLEM
What is the approximate yield to maturity for a $1000 par bond selling for $1200 that matures in 10 years and has a coupon interest rate of 12%?
a. 8.9% b. 12.7% c. 12% d. 14.2%