Question: 1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20

1. Use the data to calculate the earned value for
1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20 25 % Comp 10 6 100% 12 6 4 75% 4 5 6 596 Conceptual Design Graphics Design Copyright Samples Tooling Production Total Cumulative 4 2 25% 6 9 4 10% 2 6 14 1096 10 18 22 26 24 10 28 50 76 100 Select one a $38.850 b. $100.00 C. $13,250 d 5454 750