Question: 1 . Use the following table to create a network diagram. If there is an incentive of $ 2 5 , 0 0 0 for
Use the following table to create a network diagram. If there is an incentive of $ for the company to finish in nineteen weeks or less, is it feasible and economical for them to do so
Activity Precedes Normal Time
in weeks Cost to Crash
st week Cost to Crash
nd week
Start AB na na
A CD $ na
B G $ $
C E na na
D F $ $
E H $ $
F H $ $
G I $ $
H End $ $
I End $ na
End na na na
Yes
No
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock