Question: 1 . Use the following table to create a network diagram. If there is an incentive of $ 2 5 , 0 0 0 for

1. Use the following table to create a network diagram. If there is an incentive of $25,000 for the company to finish in nineteen weeks or less, is it feasible and economical for them to do so?
Activity Precedes Normal Time
in weeks Cost to Crash
1st week Cost to Crash
2nd week
Start A,B 0 n/a n/a
A C,D 6 $8,000 n/a
B G 4 $5,000 $6,000
C E 4 n/a n/a
D F 5 $6,000 $6,000
E H 6 $8,000 $8,000
F H 6 $7,000 $10,000
G I 8 $3,000 $5,000
H End 5 $12,000 $15,000
I End 6 $5,000 n/a
End n/a 0 n/a n/a
Yes
No

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!