Question: 1. Use the information provided in the table below. Activity Time (days) Immediate Processor 2 B 7 D 10 B E 5 AD F 6

1. Use the information provided in the table
1. Use the information provided in the table below. Activity Time (days) Immediate Processor 2 B 7 D 10 B E 5 AD F 6 G 10 EF CUNI a. Draw a precedence chart (3 points) b. What is the project completion time? (2 points) c. What is the critical path? (3 points) d. What is the sum of the slack times in total for all activities? (4 points) c. How many paths are available in total from Start to End including the critical path (4 points)