Question: 1) Using microsoft project or other project management information systems, constraints can be assigned to each resource, such as a)The number of hours or times
1) Using microsoft project or other project management information systems, constraints can be assigned to each resource, such as
a)The number of hours or times that it is available
b)The experience of the resource
2.Which of the following is true concerning additional functionality that is over and above the documented scope?
a ) Additional functionality should be leveraged to exceed the customers expectations
b)The final product should include only the functionality, documented in the final documented scope
c)Additional functionality should be channeled back through the change control process to ensure that it gets documented into the project scope