Question: 1. Using the given network, draw a gantt chart for the music festival project to level out resources allocation. Activity Description Duration (weeks) Immediate predecessors
1. Using the given network, draw a gantt chart for the music festival project to level out resources allocation.
| Activity | Description | Duration (weeks) | Immediate predecessors |
| A | Contract negotiation with selected music groups | 3 | - |
| B | Find a construction firm & build the stage | 5 | C |
| C | Contract negotiation with roadies | 2 | - |
| D | Screen and hire security personnel | 3 | - |
| E | Ticket distribution arrangements | 1 | A |
| F | Organize advertising brochures and souvenir program printing | 4 | D |
| G | Logistical arrangements for music group transportation | 1 | E |
| H | Sound equipment arrangements | 3 | C, D |
| I | Processing of travel visas (for international groups) | 5 | F, H |
| J | Hire parking staff, and make parking arrangements | 4 | E, B, H |
| K | Distribute media passes and arrange for MTV recording | 5 | G |
| L | Arrange for concession sales and restroom facilities | 2 | F |