Question: 1. Using the Information given below in Table 1, a) Draw the project network b) Calculate the Early Start (ES), Early Finish (EF), Latest Start

1. Using the Information given below in Table 1, a) Draw the project network b) Calculate the Early Start (ES), Early Finish (EF), Latest Start (LS), and Latest Finish (LF) of all the activities c) What is critical path and corresponding duration? [2+10+0.5=12.5] Table 1 Activity A B D E F G H I J Predecessors None A B B B B C, D, E, F E, F G H I Duration (in days) 3 4 4 1 1 3 N 1 2 1
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer