Question: 1. What are the differences between BAC and EAC? Explain its implications. 2. In month 9 the following project information is available: actual cost is
1. What are the differences between BAC and EAC? Explain its implications.
2. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. Explain its implication and usefulness.
3. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? Explain your answer and its implications.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
