Question: 1. What do you know about Operation Scheduling? Explain and give an example in your workplace. 2. What is the function of Operation Scheduling for
1. What do you know about Operation Scheduling? Explain and give an example in your workplace. 2. What is the function of Operation Scheduling for a company? Give an example at your workplace. 3. Case Study of Production Scheduling with Shortest Processing Time (SPT) PT. Makmur has the following machine schedule data:
| Job | Work Days Remaining | Job Due Date |
| A | 24 days | 24 days |
| B | 18 days | 18 days |
| C | 25 days | 25 days |
| D | 21 days | 36 days |
| E | 44 days | 46 days |
Determine the machine schedule using:
(a) SPT rules
(b) EDD rules