Question: 1. What does the project manager create as a result of the schedule development process? a. Schedule baseline b. Schedule rolling wave plan c. Project

1. What does the project manager create as a result of the schedule development process?

a. Schedule baseline

b. Schedule rolling wave plan

c. Project schedule

d. Schedule baseline and project schedule

2. What is the correct critical path statement?

a. It is the longest path in project network diagram

b. It is the shortest route on the project network diagram.

c. The critical path has the lowest project risk

d. The path that demonstrates how a project can be completed in the shortest amount of time.

3. Each task will have one or more predecessor and/or successor dependencies:

Select one:

True

False

4.

1. What does the project manager create as a result of theschedule development process?a. Schedule baselineb. Schedule rolling wave planc. Project scheduled. Schedule

In the network diagram, identify the critical path? B 1d 3d A 3d 2d E 2d 5d C O a. A->D->E O b. E->C->A O C A->B->D->E O d. A->C->EIn the network diagram; identify the minimum lead path? C! a. I" Days C} b. 6 Days O c. 8 Days C) d. 5 Days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!