Question: 1. What does the project manager create as a result of the schedule development process? a. Schedule baseline b. Schedule rolling wave plan c. Project
1. What does the project manager create as a result of the schedule development process?
a. Schedule baseline
b. Schedule rolling wave plan
c. Project schedule
d. Schedule baseline and project schedule
2. What is the correct critical path statement?
a. It is the longest path in project network diagram
b. It is the shortest route on the project network diagram.
c. The critical path has the lowest project risk
d. The path that demonstrates how a project can be completed in the shortest amount of time.
3. Each task will have one or more predecessor and/or successor dependencies:
Select one:
True
False
4.


In the network diagram, identify the critical path? B 1d 3d A 3d 2d E 2d 5d C O a. A->D->E O b. E->C->A O C A->B->D->E O d. A->C->EIn the network diagram; identify the minimum lead path? C! a. I" Days C} b. 6 Days O c. 8 Days C) d. 5 Days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
