Question: 1 . What information is required to create a CPM ( choose all that apply ) Question 1 options: 1 . Durtion of the Tasks
What information is required to create a CPM choose all that apply
Question options:
Durtion of the Tasks Activities
Relationship between the Tasks Activities
What coloc the bars on the bar chart will be
List of Tasks Activities
One way to break up the work into tasks Activities is to consider unique crew or trade.
Question options:
TrueFalse
One way to break up the work into tasks Activities is to consider the materials or unit of measurement.
Question options:
TrueFalse
WBS stands for
Question options:
Work Breakdown Structure
Week Before Start
Wednesday is Bowling for Sundays
Work Benefit Subscription
Every network has at least one critical path.
Question options:
TrueFalse
The backward pass defines Early Start and Early Finish dates.
Question options:
TrueFalse
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock