Question: 1. What is a project network as discussed in texbook, ppnts and homeworks and on the videos? Select one: a. A flow of activities on

1.

What is a project network as discussed in texbook, ppnts and homeworks and on the videos? Select one:

a. A flow of activities on a project

b. None of these answers are correct

c. A definition of the hierarchy of project tasks, subtasks and work packages

d. A declaration of the rules used on a project

e. A career path management system

2.

For a production system, you know that total daily output is 400 units. You also know that the total labor necessary to produce the 400 units was 350 dollars, energy was 600 dollars, capital was $1000 and materials was $1500. You want to use the cost for energy and materials to calculate the productivity ratio. What type of productivity is this and what would you calculate for this productivity ratio?

Select one:

a. It is a partial productivity ratio and the calculated ratio is .19

b. It is a partial ratio and the calculated ratio is 42%

c. It is a multifactor productivity ratio and the calculated ratio is .19

d. None of these answers are correct

e. It is a full productivity ratio and the calculated ratio is .42

3.

If what you knew about a production system was that total daily output was 400 units and the total labor necessary to produce the 400 units was $350, energy was $1000, and capital was $5000, what kind of productivity measure could you use to compute productivity if you were to use energy costs as the input? Select one:

a. Both multifactor and total measure

b. Partial measure

c. None of these answers are totally correct

d. Full measure

e. Total measure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!