Question: 1. What is the critical path? [ Select ] [ACEF, BCEF, BCD] 2. What is the expected duration of the project with variability? [ Select

1. What is the critical path? [ Select ] ["ACEF", "BCEF", "BCD"]

2. What is the expected duration of the project with variability? [ Select ] ["13.5", "24.5", "16"]

3. What is the project's standard deviation of its expected duration? [ Select ] ["2.5", "1.6", "2.1"]

4. What is the likelihood of completing the project in 17 days? [ Select ] ["74%", "68%", "84%"]

5. What is the likelihood of completing the project between 15 and 17 days? [ Select ] ["99%", "47%", "26%"]

6. There is a 90% chance the project will be completed in how many days?

1. What is the critical path? [ Select ] ["ACEF",

Consider the following scenarios for each activity in a project. Activity Preceding activity Optimistic to A Start 4 B Start 1 C A, B 2 D C 3 E 1 F E 2 5 Please answer the following: 1. What is the critical path? BCEF 2. What is the expected duration of the project with variability? 24.5 3. What is the project's standard deviation of its expected duration? [Select] 4. What is the likelihood of completing the project in 17 days? [Select] 5. What is the likelihood of completing the project between 15 and 17 days? [Select] 6. There is a 90% chance the project will be completed in how many days? [Select] Most likely tm 5 3 3 5 2 LO Pessimistic tp 9 5 7 10 3 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!