Question: 1 ) What is the critical path, time, and cost for an all - normal level of project activity? 2 ) Calculate the crash cost

1) What is the critical path, time, and cost for an all-normal level of project activity?
2) Calculate the crash cost-per-day (all activities may be partially crashed).
See column H in the table above
3) Find the optimal way of getting an 18-day delivery time.
Crash activities 1 day at a time (they can be partially crashed).
Project cost Critical activties
4) Find the optimal way of getting a 16-day delivery time. What is the project cost?
(Crash cheapest activities that impact project time using the Gantt chart until you get 16 days)