Question: 1 ) What is the critical path, time, and cost for an all - normal level of project activity? 2 ) Calculate the crash cost
What is the critical path, time, and cost for an allnormal level of project activity?
Calculate the crash costperday all activities may be partially crashed
See column H in the table above
Find the optimal way of getting an day delivery time.
Crash activities day at a time they can be partially crashed
Project cost Critical activties
Find the optimal way of getting a day delivery time. What is the project cost?
Crash cheapest activities that impact project time using the Gantt chart until you get days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
