Question: 1. what is the expected time for activity A? a. 6 1/3 b. 4 c. 5 1/6 d. 5 1/3 2. what is the variance

1. what is the expected time for activity A?
a. 6 1/3
b. 4
c. 5 1/6
d. 5 1/3
2. what is the variance for the activity A?
a. 1.00
b. 0.69
c. 0.25
d. 0.44
3. what path is the critical path?
a. b-e-g
b. a-d-f
c. a-c-e-g
4.what is the probobility that the critical path will be compleated in 23 weeks?
a. 97.7%
b. 96.7 %
c. 99.7 %
d. 98.7 %
5. what is the number of weeks required to assure a 95 percent of chance of completition?
a. 21.606
b. 23.606
c. 20.606
d. 22.606 1. what is the expected time for activity A? a. 6
Activit Pessimist Predecess Optimisti. Most ors Likely None None - oooo I bc 4 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!