Question: 1) What is the first step in developing a project scope management plan? a. Identify stakeholders. b. Create a Work Breakdown Structure. c. Create a
1) What is the first step in developing a project scope management plan?
a. Identify stakeholders.
b. Create a Work Breakdown Structure.
c. Create a project Scope Statement.
d. Collect requirements.
2)For a construction project, the house is the _______ deliverable, and the how-to instructions are the _____ deliverable.
a. Project, product
b. Product, interim
c. Product, project
d. Functional, non-functional
3)All of these are advantages of using a WBS EXCEPT:
a. To encourage a systematic planning process.
b. To ensure all dates assigned to schedule activities are within the overall project timeline.
c. To reduce the possibility of omission of key elements.
d. To simplify the project by dividing it into manageable units.