Question: 1- What should be done before sequencing the tasks on the work breakdown structure? Select one: a. Determine resource availability and the required lead time.
1- What should be done before sequencing the tasks on the work breakdown structure?
Select one:
a. Determine resource availability and the required lead time.
b. Assemble the project schedule.
c. Estimate resource requirements.
d. Estimate task durations.
2- What helps you identify those tasks that must be completed before the next task can begin?
Select one:
a. Forward pass scheduling
b. Minor path scheduling
c. Critical path scheduling
d. Backward pass scheduling
3- Which budget is most directly related to change control?
Select one:
a. Quality control budget
b. Risk management budget
c. Contingency budget
d. Administrative budget
4- What is used to determine if all required tasks have been done?
Select one:
a. Quality checklists
b. Quality metrics
c. Cost of quality (COQ)
d. Quality standards
5- What factor best describes effective communications management in a project plan?
Select one:
a. When working with project team members, a high degree of formality is needed.
b. All stakeholders should have a consult (two-way) communications relationship with project team members.
c. Communications should be limited to what each stakeholder needs to know to be effective.
d. Executives generally desire reports only at milestones.
6- An organization creates a scope/statement of work before designs are complete and some contract details are vague. What is a risk if the organization is using fixed price contracts?
Select one:
a. The contractor may pad his/her estimates.
b. The contractor may need to be paid for more overtime.
c. The contractor may insist on a higher set hourly rate.
d. The contractor may exercise the right to append the contract.
7- What does risk management NOT address?
Select one:
a. Ineffective communication
b. Conflicting priorities
c. Schedule and budget overages
d. Project failure
8- What information is a primary (main or major) input to the resource planning process?
Select one:
a. Project schedule
b. Project budget
c. Work breakdown structure (WBS)
d. Project objectives statement