Question: 1. Why is it important to use earned value management (EVM) in the overall management of projects? 2. The following activities are part of a
1. Why is it important to use earned value management (EVM) in the overall management of projects? 2. The following activities are part of a project to be scheduled using CPM: Activity Immediate Predecessor Time (weeks) 6 B 3 A 7 D 2 E BD 4 F D 3 EF 7 a Draw the network. What is the critical path? How many weeks will it take to complete the project? 4. How much slack does activity B have