Question: 1. With the process information provided in the table, when the sequence of flow is A -> B (all machines can be used) ->

1. With the process information provided in the table, when the sequence

1. With the process information provided in the table, when the sequence of flow is A -> B (all machines can be used) -> C -> D (all machines can be used), calculate: a. Maximum capacity of the process b. Effective capacity of the process [20 points] Operation No. of Design Capacity Planned Overall Overall Equipment (by equipment) Utilization Design Effective Capacity Capacity 12 ABCD 1 400 units/hr 80% 4 100, 80, 150, 125 77% 350 units/hr 95% 2 190, 235 72.5%