Question: ---- 1 You are analyzing a project and have prepared the following dat Year Cashflon 0 S169,000 546,200 2 S87,300 3 $41,000 $ 39,000 Required
---- 1 You are analyzing a project and have prepared the following dat Year Cashflon 0 S169,000 546,200 2 S87,300 3 $41,000 $ 39,000 Required payback period 2.5 years Required return 8.50% Based on the net present value of for this project, you should O-$2,021.28; reject the project O-$406.19; reject O $7,978.72; accept O $9,836.74; accept O $12,684.23; accept n